Final RAA report confirms Nu 121.61 mn in illegal overpayments and Nu 114.88 mn in wasteful expenditure on domestic airports

phone-numberMoIC Minister Lyonpo Nandalal Rai, former Director of Civil Aviation Phala Dorji and Deputy Executive Engineer Gyem Dorji held accountable for most irregularities and lapses in the report

The final RAA report on the construction of Domestic Airports issued on December 2012 has confirmed most of the findings of the earlier draft reports of the RAA with some minor changes.
Though the MoIC gave some explanations the audit has not accepted them and has upheld a majority of its original findings in the final report issued to various senior government officials.
The MoIC has been given till March 31st 2013 to come out with an action taken report to list out the action they have taken on the RAA report or provide further justifications and explanations.
The RAA meanwhile has forwarded a copy of the Report to the Anti Corruption Commission to investigate possible corrupt practices in the project (see story on pg 1).
The airports were constructed using nu 435 mn of scarce RGoB funds excluding the resurfacing works.
The report confirms Nu 121.61 mn in overpayments and Nu 114.88 mn in wasteful expenditures.
The report also covers findings on the Younphula and Bathpalathang airports (see story on pg 1).
A peculiar aspect of the report is that the MoIC minister is involved in several violations that would normally be committed by tender committee members. This is especially because ministerial tender committees do not include ministers.
The report says that the Gelephu and Bathpalathang airports did not meet the required pavement thickness compromising the safety of aircraft and passengers.
The Auditor General in the covering letter of the report says, “The auditors review revealed lapses of serious nature involving improper planning and preparation of estimates, inappropriate evaluation of tenders, inflated claims, acceptance of substandard works, excess payments to contractors etc.”
The report says that many procedures were violated on the pretext of completing the airports on time.
However, it says the neither the objective of rendering the domestic air services operational within the stipulated timeframe was achieved nor was the value for money in the implementation of the project ensured.
The information on the final RAA report was shared with this paper by whistleblowers who want this information to come out in the interest of transparency and accountability.

Gelephu Airport
In the draft RAA report the bulk of the illegal overpayments and wasteful expenditure occurred in the Gelephu Airport. This has been reconfirmed in the final audit report.
Overpayments and unjustified payments
The final RAA report confirmed four instances of overpayments and unjustified payments made to the contractor Tashi Kunzom Construction.
The RAA report confirmed Nu 78.27 mn was overpaid in double payments due to inflation of the quantities of the work done. The work was for providing and laying out ‘Dense Bituminous Macadam’ (DBM) and ‘Asphalt Concrete’ (AC) on the airport surface.
The report also confirmed excess payment of Nu 24.94 mn for earthwork excavation and transportation of soil and rocks in the construction of the airport.
The report also confirmed Nu 23.67 mn in unjustified payment on transportation of spoil material.
The RAA has found Nu 6.96 mn in excess payment for blacktopping of the runway pavement using DBM and AC.
In all the above cases the RAA has asked the MoIC to recover the money within the three month period till March 31st 2013 beyond which a penalty of 24 percent per annum would be levied. The RAA has also asked for the Ministry to investigate possible collusion in all the above cases.
For the above cases, the direct accountability is on deputy executive engineer Gyem Dorji and supervisory accountability on Phala Dorji.
The report says that it may be advisable to not to ply any flights until the runway is brought to acceptable practices.

A financial impact of Nu 64.54 mn
The RAA report points out that failure of the Ministerial Level Tender Committee and in particular the Evaluation Committee which failed to evaluate the tenders with due diligence resulted in a loss of Nu 64.54 mn.
This was after the RAA found that the BOQ rate of the contractor Tashi Kunzom Construction was much higher than the BSR 2009 rates of the government.
The report says considering the huge adverse financial impact on the cost of the project, it is imperative for the ministry to go thoroughly review the circumstances leading to inappropriate stipulation of technical specifications in the BoQs.
The report has laid the direct and supervisory accountability on the Ministerial level tender committee.

Conflict of Interest
The RAA report has held the MoIC Minister directly accountable for possible existence of conflict of interest in the contract. The minister was held accountable for insisting on going ahead with the construction process in the absence of surveyors with the result that the contractor did the Topographical survey.
The RAA has said that conflict of interest cannot be ruled out when the contractor was asked to do the Topographical survey which should have done by the Department and later execute works based on it.
The topographical survey is a fundamental exercise for not only facilitating preparation of designs, drawings, estimates, BOQs but also forecasting realistic amount of earthwork excavation.
“There was no monitoring and overseeing mechanism put in place to validate the correctness of the topographic survey report,” says the Report.
“Further, non quantification of earthworks even after the conduct of topographic survey has lead to a huge deviation in the quantity of earthwork excavation between the estimated quantity of 28,635.00 m3 and actual executed and paid quantity of 581,885.040m3 representing +1932% deviations from the estimates,” says the Report.

Relocation of original site and flood prone airport
RAA in its survey found that ignoring the consultant’s information around 500 meters of the original site of the airport had been excavated before it was relocated. This has resulted in wasteful expenditure of Nu 4.21 mn in earthworks. The RAA has asked for more details on the work done on the first site to gauge the actual wasteful expenditures.
The RAA also pointed out that not following the consultants advice that had been paid Nu 5.6 made the expenditure worthless.
The relocation of the airport had also increased the distance between the building runway and the airport terminal from 246 meters to 374 meters.
The consultants, following a thorough study on flooding risks of the airports recommended that the runway elevation should be at least 322 meters at its lowest point. However, the lowest centerline was only 266.524 meters above sea level. The RAA report says that this could be one of the plausible reasons as why the Gelephu airport was threatened with flooding during the construction phase in last monsoon.
Here too the MoIC Minister was held directly accountable as the above had happened under his instructions.

Ambiguity in planning, estimations and implementation
The RAA noted that the estimates for the contract package especially for the earthwork excavation and construction of runway were not prepared as per the required construction norms. The DCA had not conducted any preliminary studies such as hydrological, geotechnical and geodetic data as these are the basic and critical information for execution of such vital construction work.
As a result the RAA found huge deviations in earthworks going up to 1,932 percent which it said was due to flaws and ambiguities in earthwork quantification but also unrealistic preparation on BOQs. The RAA says this all adversely impacted the project cost.
The MoIC in its reply said, “the honorable minister although appreciated the concern brought out, the need for conducting such studies was not felt as an urgent issue since flooding at Gelephu was not seen in the past years and to mitigate vulnerability against flooding river channelizing was agreed upon”
The RAA says the non-conducting of such surveys impeded the economy, efficiency and effectiveness in the project implementation and impeded value for money.
The RAA placed direct and supervisory accountability on the MoIC Minister.

Intransparency in the tendering process.
The DCA despite repeated requests failed to provide bid evaluation results to the RAA. The information provided by DCA could not be verified as the re-tendered documents of the three contractors were not made available on record except the Standard Bidding Document (SBD) of M/s Tashi Kunzom Construction.
The RAA has, however said, awarding the contract to Tashi Kunzom Construction whose bid was higher compared to Bhutan Engineering Company lacked transparency and fairness. It said existence of possible conflict of interest and corrupt practices could not be ruled out.
The direct accountability was placed on Gyem Dorji

Nu 34.27 mn defective fence
The RAA found that despite a Nu 34.27 mn fencing the Gelephu Airport still remains unsafe as the fencing has been damaged and washed away in parts the river and season stream. The fencing was also not constructed along the national highway at all due to insufficient budget.
The DCA has agreed to repair the fencing works and also deduct excess payments of Nu 49,858.

 

RAA’s final report confirms

Nu 121.61 mn in illegal overpayments

Nu 114.88 mn in wasteful expenditure

Compromised safety of airports

Acceptance of substandard works

Ineligible bidders chosen and eligible one disqualified

Possible collusion and corrupt practices

Conflict of Interest

Nu 435 mn for construction of three airports

Intransparency and adhoc decisions

Tender rules violated

 

 

Check Also

Loan deferral to be more targeted after June 2024

The loan deferral is coming to an end for various sectors in June 2024 and …

30 comments

  1. One more, making it 3. Or is the report politically motivated? Is RAA also playing the role of opposition? Expect more storm before the election?

    • Wai! Zhaw yondu. Yes RAA is also playing the role of opposition, you’re definitely right and soon ACC will play in same role. Because the RAA has forwarded a copy of the Report to the Anti Corruption Commission to investigate possible corrupt practices in the project. And after that court will play opposition role. Lastly Shinjey Chhoegyal Gyalp will play i.e after death.   

  2. So there goes another DPT candidate out of the coming elections. Nandalal will now not get audit clearance to contest but this at least means the opportunity could be given to a stronger candidate.

  3. Wow! Zhaw yondu, our nation need transparency and correct accountability and this is right way to fix, and must be fixed, one by one, step by step, then only young and desperate will grow.. 

  4. All the three airports completed at Nu.435 millions and out of it you mean to write that Nu.236.49 are illegal and wasteful payments. Is it possible to construct three airport with just Nu.198.51 million. It looks impossible tasks, that is 54.37% of the total cost.Can any one believe! May be my understang on the issue is not very clear. Can anyone limelight on it? A building in Thimphu cost Nu.150 million and a flat at Kabesa cost Nu. 80/- million.

  5. you can shake it

    That is why Jigmii yezor thrinley was worried when it comes to RTI. Did they pay their dues using this money??????

  6. We should hang or jail the corrupt people like it is done in China. If few people take benefit of the donor funds, what will rest of the people in Bhutan have.

    Time has really come for tightening the corruption and new political parties should take note of this and make a difference during their time.

  7. Its high time RAA also gave out details of the Bhutan lottery then maybe we will see few more out of the elections.
    Honestly,RAA please show the audit report which you denied the OL to see and never gave it to the National Assembly for review.
    Even the ACC was denied the report.A covering letter was sent only.This could be the next bomb!!

  8. Every body is corrupted bastards……

  9. These days the air is full of complaints – and vice versa – and there is nothing that works faster than a brain that seeks excuses for wrongdoing. Even people of modest intelligence can think of excuses in a flash. It appears that people employed to make serious decisions on our behalf seem impervious to reason. It must come with the pedigree.The last thing they want is reality getting in the way.The reason why political careers continue to defy gravity and plummet upwards is that where’s there’s a will, there’s a loophole. The backing soundtrack is the tribal din of protection.

  10. Its better for Nandalal to go back to where he belonged five years back, Person of his caliber should not have been made minister on first hand. Its the fault of the DPT chief who wants to be one man eyed king in the kingdom of bind. Whatever may be, we should salute this paper for bringing in this news in public domain…..keep it up The Bhutanese and make us proud….

  11. GIVE NO HAPINESS GET NO HAPPINESS

    All ministers r chor.

  12. It was duty of the MoI to construct three airports as per plan and they have achieved it. As mandated, it is the duty of RAA to audit all agencies in the country. Hence, they have audited the airport contruction project and pointed out some flaws as they can not give clean chit to any agencies they audit otherwise they will not be endowed another medal in future. Finally, the Bhutanese as claimed got hold of this report through whistleblower and published it in their paper as Part-I, Part-II, Part-III, Part-IV to make it very attractive to defame the serving Govt. The case is very clear! What do you readers say.

  13. Why our PM JYT is silence …

  14. Deputy Executive Engineer owns santefee car after that project. find out…..ACC???

  15. There should be death penalty for missuing public money and common resources. It is good to start with those who are implicated in the RAA report.

  16. It is also time, we change Audit rules and regulation. Found out audits are more into procedures and less into others.

    Audit should know how to judge effectiveness, efficiency and performance but am not defending this case

  17. Mr. Pema, I am not a DPT member ya!

  18. It’s all due to retarded feudal lord ministers.

  19. All the corrupted people should be punished according to our law whether it is me, my father or any of my family members or any Bhutanese of this country. No one is above law.

  20. @CORAL,
    I like your attitude! If there are 100,000 people of your version out of 700,000 population, Bhutan will be another SINGAPORE. Wah! GREAT.

  21. CORAL I FULLY SAPORT YOU MAY ,, ,,,,,

  22. I dont know why people are trying to drag in Lyonpo Nandalal because of this issue. For instance I work for the Dept of Livestock and in case of any problems…the memo will be upon my name…Not my minister….No wonder…This newspaper is always politically motivated. We should be proud of the fact that because of democracy he gets to become a minister….

  23. Why should Nandu be part of the Ministerial Tender Committee, supposed to be chaired by the Secretary? or did Ace Kinley intentionally play a safer role or was he never in the ministry but globe-trotting? I agree that “Public Information is Public Property” but fully disagree to TB’s assumption that a draft document is a public document. I just see this fiasco as a revenge to Nandu for his circular to stop giving ads to TB…

  24. Inservice
    Yes, Yes- you are correct.this paper is fixing the accountability of Lyonpo Nandalal as if it RAA themselves. Shame on the Bhutanese.

  25. To fellow friends,
    our nation must need transparency and the bhutanese has done right thing, what other news papers and media doing? – just nothing, just covering lousy news. for any discrepancies from any department and eventually ministers are sure to be blamed and they should be blamed. RAA and ACC should be stronger than this, they should be doing better coz many corrupts escaped unhurt, but innocence are tight necked. so this nation need a clean and who ever wind in forthcoming elections there should never be land slight victory, if it again happens then it is only going to be worse… better than the best 

Leave a Reply to Pema Cancel reply

Your email address will not be published. Required fields are marked *